Audit: Poor MBTA planning cost $11M

Posted: Updated:
BOSTON (AP) - A state audit has found that the MBTA wasted more than $11 million on three major station renovation projects because it failed to craft more thorough designs and get community input earlier in the planning process.

The state auditor's report released this week said last-minute changes in the projects for Kenmore, Maverick, and Ashmont stations, including extra stairways, larger elevators, and a new roof deck, cost much more than if they had been included in the initial plans.

The three station renovations cost a total of almost $147 million.

Massachusetts Bay Transportation Authority officials tell The Boston Globe the agency's planning processes have changed in the years since those projects began, pointing to more transparency and the significant role now given to community meetings.

  • Stay Connected

  • Like Us on Facebook
  • Follow Us on Twitter
Powered by WorldNow

WHDH TV 7NBC WLVI TV CW56
Sunbeam Television Corp
7 Bulfinch Place
Boston, MA 02114

News Tips: (800) 280-TIPS
Tell Hank: (855) 247-HANK
Corporate Media Services: (800) 642-1551

Can't find something?
Connect with us here:
Powered by WorldNow
All content © Copyright 2000 - 2014 WorldNow and WHDH. All Rights Reserved.
For more information on this site, please read our Privacy Policy and Terms of Service.